Breaking up can be hard to do. Commercial contracts sometimes create difficulty in when a party wishes to terminate; this may be avoided with a modicum of foresight and contemplation of what might happen in the event of fallout between the parties at the outset of the contract. here, we consider the four ways which a contract may be brought to an end and terminated.
A contract is usually terminated when both parties have performed all of their respective obligations under the agreement. At this time, both parties have fulfilled what they promised to do at the outset of the contract. Other avenues are available to the parties for termination of contracts, such as by agreement and for breach of contract.
There are four ways in which a contract may be discharged.
Discharge by performance is where both parties to a contract have performed all their primary obligations under the contract, including all express and implied terms. There are three elements required to be satisfied to say, at law, that performance is complete.
Each of the parties is required to perform their obligations under the contract with perfect precision. Any deviation from the contractual obligations will amount to a breach of contract. In the case of Bolton v Mahadeva (1972), it was held that a contractor could not claim payment for a central heating system which did not work properly as it did not fulfil the primary obligation of heating the house. In some cases, performance is not strict and the obligation is not to achieve a specific result, but merely to exercise reasonable care and skill.
Where a contract requires strict performance there are circumstances in which the law may allow payment for part performance of a contract or incomplete contracts on a quantum meruit basis which enables the party performing to get paid fair and reasonable remuneration for their work where:
When a party to a contract "tenders performance", that is, attempts to perform their primary obligations under the contract and is prevented from doing so, that person may be considered to have discharged their obligations under the agreement, thus terminating the agreement. if the tendered performance is refused by the other party, they may be sued for breach of contract, and thus the further performance is not required but the debt arising under the contract for products or services is not.
A contract may be discharged by agreement in a number of situations.
Where both parties consent, the mutual obligations to perform contractual obligations will come to an end. Where a contract is discharged in this way, as with any contract, the agreement must be supported by consideration be legally binding. Where both parties have performance obligations outstanding under a contract, an agreement between the parties to discharge those obligations will be enough to satisfy the requirement for consideration, making the termination legally binding.
However, where one party still has performance obligations under the contract, for the agreement to be legally binding there must be either:
It is always open to parties to agree to variations to their contractual arrangements. This is put in place by executing a new agreement which supplements the first (rather than entirely replacing it). In some circumstances, the original contract may be discharged in its entirety and replaced with a completely new contract. In either of these circumstances though, the existence of a separate agreement must be proved. Accordingly, it is best recorded in writing.
A contract may be discharged by a condition subsequent which is a stipulation of a state of affairs which causes existing contractual obligations to come to an end. The state of affairs does not necessarily have to be out of the control of the parties.
When a breach of contract takes place, it does not automatically discharge a contract. If the breach amounts to a breach of a condition of the contract (ie a repudiatory breach), the innocent party has the option of either
There are situations in which the innocent party wrongly treats the contract as repudiated by the party in breach, and purports to terminate the contract. This is repudiation of the contract by the innocent party for what is a non-repudiatory breach is a breach of contract in its own right, entitling the other party to treat the contract as discharged. This took place in Federal Commerce and Navigation v Molena Alpha (1979), where the owners of a ship wrongly believed they were entitled to repudiate the contract. The court held that the repudiation was wrongful and therefore the other party could treat the contract as discharged.
Where a contract is treated as terminated in this way, the performance obligations under that contract are discharged at the date of termination. However, performance of secondary obligations, such as (1) to maintaining the confidential information of the other party, and (2) the obligation to pay damages for any losses caused to the innocent party, are not discharged and continue in force.
Anticipatory Breach
Anticipatory breach of a contract may be either explicit or implicit. Anticipatory breaches take place where one party expresses an intention by either not performing their obligations under the contract or performing them in a way in which is inconsistent with the original contractual terms. In these circumstances there are a number of options available to the innocent party.
The innocent party may wait and allow the party in breach to properly perform their obligations. If the part in breach does so, then the right to terminate will be lost. The innocent party may also sue for damages as soon as the anticipatory repudiation occurs, and not wait for the date of performance. The innocent party also has the option of affirming the contract by performing their obligations under it. In the case of White and Carter Limited v McGregor (1962), the defendants cancelled the contract, but the claimants refused to accept the termination and continued with performance under the contract, later suing the defendants for the full contract price. The Claimants were successful in doing so.
The option of accepting the repudiation or terminating the contract is not available where the innocent party requires the cooperation of the other party to perform the contract or if they have no real interest in performance of the contract.
Discharge by frustration occurs where it is impossible to perform the obligations under a contract due to a subsequent change in circumstances. It is the nature of the outstanding contractual obligations which must have changed.
The modern test for frustration is outlined in the case of National Carriers v Panalpina (1981). Frustration occurs when:
... there supervenes an event (without default of either party and for which the contract makes no sufficient provision) which so significantly changes the nature (not merely the expense or onerousness) of the outstanding contractual rights and / or obligations from what the parties could reasonably have contemplated at the time of its execution that it would be unjust to hold them to the literal sense of its stipulation in the new circumstances.
Frustration may occur in a number of situations:
The Doctrine of Frustration will not apply when:
We have set out the fundamental ways and means by which a contract may be brought to an end. Professionally drawn contracts may contain other means by which the contract may be brought to an end without suffering loss, such removing any rights to damages or recovery for loss, providing for termination for convenience of a party, warranties that presuppose a state of affairs as at the time of the contract that has not eventuated. Moreover, damages claims may be limited to specified sums or avoided in their entirety provided the innocent party does not fulfil their duty to mitigate their loss in the circumstances.
For business legal advice and more information on repudiation of contracts and termination of contracts, contact us online or call us on 020 7353 1770.